Where Bird Key Drive meets the John Ringling Causeway, the intersection is now a work zone with a 35-mph speed limit. The bike lanes are closed and cyclists are sent to a posted detour. Crews are widening and paving the road, pouring curb and sidewalk, laying drainage, and installing the light poles and traffic signals that will control the turn onto Bird Key. The Florida Department of Transportation's project 445926-2 covers S.R. 789 from Bird Key Drive to east of Sunset Drive. In the weekly Traffic Watch dated October 13, the agency still lists the estimated completion as "early 2027."
So this winter season will run with the work zone in place. And the most important design decision at Bird Key's entrance went to the car turning toward downtown, not to the pedestrian.
An Arrow Built for the Drive Into Town
The project adds new traffic signals at three intersections: Sunset Drive, Golden Gate Drive and Bird Key Drive. The Bird Key Drive signal got a change after the plans were drawn. On February 10, 2026, FDOT engineers and city staff met in the Bird Key Park car park at 200 John Ringling Blvd. to look at the crosswalks there. The meeting notice noted the site was "within an active construction zone."
The city engineer's follow-up email, which is a public record, laid out what came out of the meeting. FDOT will install a northbound right-turn "overlap" arrow "to provide additional protected time for vehicles turning eastbound." That means a five-section signal head and updated signal timing.
In practice, Bird Key Drive comes up to the causeway from the south. A northbound right turn is the turn a Bird Key resident makes to head east over the Ringling Bridge toward downtown. With an overlap arrow, that right turn gets a green arrow that keeps running into the next phase of the signal cycle. So the turn has protected time instead of waiting for a gap in traffic coming off the bridge. FDOT's signal plans call the causeway the major street and Bird Key Drive the minor street, with design speeds of 35 mph and 25 mph. The arrow tilts that balance toward the minor street for the one move most Bird Key trips start with.
The arrow isn't presented as final. The same email says FDOT and the city will "monitor operations to evaluate whether this improvement addresses the current safety and access concerns," and all parties agreed to reassess once it is working.
The Road Itself Is Getting Taller
At Bird Key Drive, the road is also being raised. The Lido Key Residents Association's project summary says drainage upgrades will raise the roadway about 8 inches on average at Bird Key Drive and about 1 foot on average at Sunset Drive. The seawall cap near Sunset Drive will go up by 2 feet to match the adjacent seawall near 660 Golden Gate Point.
City Commissioner Jen Ahearn-Koch explained the reason for the raise in a January email reported by The Sarasota News Leader. The stretch between the Gulfstream Avenue roundabout and the base of the bridge "is a low point and floods horribly during rain events," she wrote, and "the stormwater should flow better" after the redesign.
The same summary lists the other changes that will shape how the intersection feels once it's done:
- Longer bus-only lanes
- Sidewalk-level bicycle lanes at the Bird Key Drive and Sunset Drive intersections
- Dedicated bicycle signals
- Shorter pedestrian crossing distances
- Tighter turning radii to slow right-turning vehicles
The last item sits in quiet tension with the arrow. Cars turning right out of Bird Key get more protected green time, and the tighter corner keeps them from taking that turn fast. FDOT has said the whole $12.3 million project is meant "to reduce travel times between downtown and the barrier islands."
Where Things Stand the Week of October 22
The work zone affects different trips in different ways right now. As of FDOT's most recent updates:
| What | Status now | What's next |
|---|---|---|
| Causeway speed limit | 35 mph, fines doubled when workers are present | Stays until construction ends |
| Bike lanes | Closed; cyclists follow a posted detour | Sidewalk-level lanes with bike signals at Bird Key Drive |
| Pedestrians | Use designated paths and posted detour signs | Shorter crossings at the new intersections |
| Sunset Drive at the Ritz entrance | Temporarily closed for driveway reconstruction | Expected to reopen by October 23, weather permitting |
| Work hours | Mostly daytime, occasional night work | Lane closures continue by phase |
| Whole project | Widening, paving, curb, drainage, signals | Completion forecast early 2027 |
The Sunset Drive date comes from the Coalition of City Neighborhood Associations, which passed along FDOT's October 5 report that work "appears to be progressing on schedule." That puts the reopening one day after this post comes out. FDOT also warns of nighttime noise from backup alarms, pumps and power tools during night shifts.
The timing drew pushback from the start. When work began in January, the News Leader found public comments asking why it was starting "just as we enter the busy season." One commenter said the daylight drive on and off the island in tourist season "can be upwards of 30 Mins without construction." With completion now set for early 2027, a second season will overlap the work zone.
The Crosswalk Question Moved to Another Project
The February site meeting was called to talk about crosswalks, and the crosswalk is the part left unsettled. The city's account says that if more measures are needed, "a west-side crosswalk may be incorporated as part of the future Little Ringling Bridge project, with construction anticipated in summer 2028."
The turn arrow comes with this project, and FDOT and the city will then watch how the intersection works. A crossing on the west side of the intersection, if it comes at all, would arrive with a different bridge project about a year and a half after this one finishes. Anyone who walks from Bird Key to Bird Key Park on the north side of the intersection, or crosses there on a bike, will use the redesigned crossings this project delivers. Whether a west-side crossing joins them is a 2028 question.
Off the Island Without the Car
The new bus-only lanes matter most to the Bay Runner. The free trolley is a joint City of Sarasota and Sarasota County Breeze service that runs seven days a week between downtown Sarasota, St. Armands Circle and Lido Key. According to Sarasota County's Breeze specialty routes page, Route 78 runs from 7 a.m. to 10 p.m. Sunday through Thursday and until 11 p.m. Friday and Saturday. Each trolley carries an exterior rack for two bicycles. The county's route map, marked "Effective December 2025," estimates a trolley every 30 minutes, subject to traffic.
In November 2023, Your Observer reported that a Bay Runner stop had been added near Bird Key Park at John Ringling Causeway and Bird Key Drive. While the bike lanes stay closed, the trolley's bike rack gives cyclists another way across the causeway. Check the stop on the county's route information before you count on it this season.
Two Things Due Back at the Beginning of 2027
The intersection isn't the only Bird Key fixture on an early-2027 schedule. In June, Your Observer reported that Bird Key Yacht Club Commodore Saul Landesberg aims to keep the clubhouse rebuild on budget and on schedule, with an "anticipated completion date at the beginning of 2027." In the meantime, members have kept club activity going without a clubhouse. If both schedules hold, the island's front gate and its club will come back into full use within weeks of each other. The crosswalk on the west side of Bird Key Drive will still be on the city's list for 2028.
Changes at the gate affect your daily drive and how a Bird Key home looks to buyers. If you're planning a sale, a purchase or a renovation around the 2027 timeline, Coastal Reserve can talk through how the finished intersection and the season ahead fit your plans. Request a confidential consultation.