The low ridge of sand between the Lido Beach Pavilion and the south end of the key is the first dune renourishment the City of Sarasota has carried out on Lido Beach. Most of the sand was dredged from New Pass, the channel along the north edge of Lido Shores. As of mid-October, the sand was in place, the posts, ropes and signs were up, and crews were planting.

The city's project page lists completion as "Early 2027," well after the 60-day construction window that opened September 21. A maintenance period is planned after planting so the plants can take root, and until the project wraps up, the ropes and signs set the shape of the beach walk.

Sand That Traveled About a Mile

The sand plan changed between spring and fall. In April, City Engineer Sage Kamiya told Your Observer that the contractor would truck about 3,000 cubic yards in from an approved inland mine, which meant 215 to 300 dump truck loads.

By the time crews arrived, the plan had switched to a closer source. According to the Coalition of City Neighborhood Associations, the U.S. Army Corps of Engineers had stockpiled about 3,000 cubic yards of beach-compatible material on the beach near state reference monument R-41 during its New Pass maintenance dredging. The dune contract covers grading that stockpile into shape, planting the full length of the dune and installing post, rope and signs at the beach accesses.

So for Lido Shores, the sand had a short trip. Material pulled from the pass at the top of the key went into a dune a short walk south of the neighborhood, and a few hundred truck trips the April plan called for never had to come over the causeway.

This is also the second time in a year that the beach has been rebuilt. The city's dredging and renourishment phase ran from January through April 2026 and was designed to produce roughly 200,000 to 300,000 cubic yards of sand on Lido Beach, aimed at stretches that had lost up to 90 feet of beach to erosion. The dune comes second and is much smaller, about one percent of that planned volume, sitting on top of a beach that was just widened.

Built to Stay Low

"It's not going to be very high," Acting Assistant Engineer Alex Davis-Shaw told WWSB. The station reported that the dune tapers gradually and leaves the view of the water open. The numbers back that up.

Measure Figure
Dune height About 2.5 feet, added on top of the existing 4-foot beach berm
Crest elevation +6.6 feet NAVD88, matching the 25-year storm water elevation
Width About 30 feet, with a gradual taper
Length About 1.2 miles, between monuments R-37 and R-44
Sand About 3,000 cubic yards
Total cost $1.2 million, with nearly $700,000 for construction
Funding 50% tourist development tax, 50% Florida DEP grants

Kamiya told Your Observer that the 2024 hurricanes "hit pretty hard," leaving only remnants of dunes in some places and scattering the sand onto roads, parking lots and into homes. He said the new dunes raise the beach's protection from a 10-year storm to a 25-year storm. Since half the money comes from the tax on hotel stays, visitors paid for a good share of a project used mostly by people who walk this beach every week.

Sixty Days for the Sand, Months for the Roots

  1. September 14: staging began.
  2. September 21: construction started. Sand went down at the north end first because there were still sea turtle nests to the south, and turtle monitoring is part of the contract.
  3. Three to four weeks in: sand placement wrapped up, as planned.
  4. October 14: sand placed, crossover posts, cables and signs installed, planting underway.
  5. Around November 20: the end of the 60-day window, counting from September 21. No one has announced this date. It is simple arithmetic.
  6. Early 2027: the completion date the city lists.

WWSB listed the species going in: dune sunflower, railroad vine and, in some sections, sea oats. These are the plants meant to hold the dune together. Your Observer reported that a maintenance period follows planting to make sure the plants take root. The posts and ropes mark where foot traffic belongs while that happens.

How the Crossings Work Now

Expect a different kind of crossing. At a March 2025 public meeting, the city described the access points as gradual paths cut through the dune and lined with post and rope, rather than raised walkovers with steps. City staff said they planned to enforce local and state dune protections and send beachgoers to the marked openings.

Some details for the north-end walk:

  • Number of crossings. Your Observer reported more than 30 beach access locations during and after the work, each lined with post and rope.
  • Three wooden walkovers replaced. Your Observer named the walkovers at the Lido Beach Pavilion, at the north end of the Pavilion parking lot and at the North Lido Beach access near the curve where John Ringling Boulevard meets Benjamin Franklin Drive. The North Lido walkover is the one closest to Lido Shores.
  • Signs. The 2025 meeting said the signs at the crossings would cite the ordinances and statutes that protect the dune.
  • Dogs. The city's Lido Beach page says pets are not allowed in the park or on public beaches, except trained service animals.

The city has described the shape of the project in two ways. Its project page says the dune runs from the Lido Beach Pavilion to the southern residential properties. WWSB reported that the dune ties into the existing dunes in North Lido Park and runs south through South Lido Park toward Ted Sperling Park. The 2025 meeting minutes say it stops at the Sarasota County park at the south end. Either way, a walk south from Lido Shores starts at the old dunes in North Lido and continues onto the new ones.

WWSB also reported that the dunes will give sea turtles and other wildlife habitat. The turtles shaped this fall's schedule too. Nests still on the south beach in September are the reason the work began at the north end.

Around the Pavilion This Season

The Pavilion is still where most people cross, and it isn't fully open. The city's Lido Beach page says the Lido Beach Pool is closed until further notice for essential repairs and maintenance, with no reopening date. It also lists free parking next to the beach and Lido Island Grill as the concession, with hours that depend on beach activity.

At the far south end, Sarasota County commissioners have asked staff to request state approval for a slow-speed, minimum-wake zone around Ted Sperling Park, WWSB reported. It is still a proposal and not yet a rule.

The city's project page has a sign-up for email updates, and that is where any change to the early 2027 completion date should show up first.